Ventilation equipment for a potato storage (intended for 3600 tons 2)

Objective

In designing the microclimate system, specialists tried to make the most out of the banked building.

The air inflow and exhaust were implemented using just the roof.

To design an insulation system to protect intake and exhaust valves from precipitation.

Solution

We used a perforated air-circuit system.

Distinguishing features

Operational stages:

  • Project development
  • Purchase of equipment and materials
  • Delivery
  • Installation
  • Start-up and adjustment operations

Design engineers and the construction department were in charge of the project, as well as Agrovent specialists in the area of ventilation equipment.

We have been in collaboration for three years. During this time, over 12 potato-storage projects have been implemented.

More projects