Development of a microclimate system for a cabbage container storage with a capacity of 7 000 tons.

Client

“FerElGam” LLC is a major producer of salted and fermented products sold in grocery stores across Russia.

Objective

To develop a year-round storage facility with the option of making daily product shipments.

To fabricate and install the system in just eight weeks.

Solution

Dragon technology was used, and the ventilation unit was equipped with remote air coolers.


Installation of asingle-mounted spray humidification system.

CO2 removal system without valve opening.

Four storage sections were equipped with a centralized automation system.

Distinguishing features

Operational stages:

  • Project development
  • Purchase of equipment and materials
  • Delivery
  • Installation
  • Start-up and adjustment operations

Design engineers and the construction department were in charge of the project, as well as Agrovent specialists in the area of ventilation equipment.